November 12, 2026
The barrels and lane shifts on U.S. 322 this winter sit east of Garnet Valley, between Chelsea Parkway and I-95. The stretch that runs past Foulk Road, Garnet Mine Road and Colonial Drive has seen one advance safety fix so far, and its main contract hasn't started. PennDOT estimates it at $167 million, which makes it the most expensive of the four contracts in the Conchester Highway program.
For a Garnet Valley driver, that means two different timelines. The current work slows the trip toward I-95 and Route 452 through 2027. The work that will change how local streets meet the highway is still being designed.
PennDOT's U.S. 322 Improvement Program covers 6.7 miles of Conchester Highway in Concord, Bethel and Upper Chichester townships. It's split into four main construction contracts. Here's where each one stands in November 2026:
| Section | Limits | Cost | Status |
|---|---|---|---|
| 101 | U.S. 1 to just east of Clayton Park Drive, 3.1 miles | $62,644,459 | Done; built spring 2017 to December 2020 |
| 102 | East of Clayton Park Drive to Chelsea Parkway/Bethel Avenue, 2.0 miles | Est. $167 million | In final design |
| 103 | Chelsea Parkway/Bethel Avenue to east of Route 452 | $99.4 million | Under construction; scheduled to finish in 2030 |
| CSX | CSX railroad bridge and Bethel Road interchange, about one mile | $63.4 million | Under construction; scheduled to finish in late 2031 |
The Garnet Valley section costs more than Sections 101 and CSX combined. It's also the only one without a contractor. The Section 102 page lists the general contractor as TBD, the start as late 2028 and the completion as TBD. It also says the section "remains in design" and that the details shown are subject to change. PennDOT's October 27 construction update says final engineering is moving forward on Section 102 and that the section is "not yet scheduled for construction."
When Section 102 is finished, it will complete PennDOT's improvements to U.S. 322 between Baltimore Pike and I-95.
The work going on now is east of Chelsea Parkway, and the two active contracts overlap there.
Section CSX has the headline price of $63.4 million. JD Eckman Construction Inc. of Atglen is the general contractor. The October 27 update says the work is paid for with 80 percent federal and 20 percent state funds. According to PennDOT's fall update, crews spent almost six months on utility work before moving traffic in mid-October. Westbound traffic now uses a single lane on the north side of the highway, and eastbound traffic uses a single lane on the south side. Here's what PennDOT has scheduled for the rest of the year:
A PennDOT District 6 release dated October 14 lists around-the-clock median lane closures on eastbound 322 between I-95 and Route 452 and on westbound 322 between Route 452 and I-95, both through Monday, December 21. It also lists weekday flagging on Bethel Avenue between the 322 overpass and Keystone Road from 8 a.m. to 4 p.m. on the same schedule, and PennDOT warns drivers to expect delays.
Section 103 is just to the west of the CSX work, and traffic there is down to one lane in each direction. A November 6 notice adds occasional overnight lane closures from 7 p.m. to 6 a.m. through the end of 2027. They'll be on 322 between Chelsea Parkway and Bethel Avenue and on Route 452 between Meetinghouse and Story roads. Oliver Lane at Kates Glen is also closed so crews can build a cul-de-sac, which removes the connection from Kates Glen to Flora Lane.
The December 21 date covers the current round of median closures. In early 2027, PennDOT plans to move eastbound and westbound traffic onto one side of the highway. That becomes the long-term pattern while crews take down and rebuild half of the CSX bridge.
The March 19 announcement about the start of the CSX contract expected demolition in spring 2027 and said the first stage would take about two years. It described the CSX job as about five years of construction and said more off-peak restrictions and detours would come in stages along the way.
The finished CSX section will be about one mile of rebuilt, wider highway with more vertical clearance over Bethel Road and the railroad. The Bethel Road interchange will be redesigned for safety and to give large vehicles better access. PennDOT is also adjusting the I-95 ramps slightly to make room for a future rebuild of that interchange. At Route 452, Section 103 will replace the 322 bridge over Market Street and rebuild the interchange. It adds westbound ramps and eastbound ramps at Dutton Street and Bethel Avenue, plus a signal at Bethel Avenue and Market Street.
Section 102 hasn't started, but one part of the Garnet Valley stretch is already finished. A PennDOT safety project done ahead of Section 102 realigned Garnet Mine Road near 322 and closed its access to and from eastbound 322.
During an earlier temporary closure of the Garnet Mine Road ramp, a PennDOT release posted by Bethel Township sent traffic along Garnet Mine Road, Larkin Road, Bethel Road and Chelsea Parkway.
PennDOT's current concept for the section makes these changes, and each one is still subject to change.
Foulk Road. The Route 261 interchange gets the biggest rebuild in the Garnet Valley section. The current plan calls for a wider replacement bridge over 322, new westbound ramps with signals, and eastbound ramps to and from Garnet Mine Road. Foulk Road and Green Glen Drive would be realigned.
Colonial Drive. PennDOT plans to end left turns from Colonial Drive onto westbound 322.
Sommers Lane. The current concept cuts Sommers Lane off from 322 with a cul-de-sac on the north side.
Bethel Avenue. Instead of meeting 322 directly, Bethel Avenue traffic would go through Chelsea Parkway and Chichester Avenue. The plan for that intersection builds a "T" intersection at 322 and Chelsea Parkway and rebuilds Chelsea Parkway from Chichester Avenue up to 322.
Creek Parkway and the new commercial road. Section 102 adds a Bethel Township Commercial Road along the south side of 322 between Foulk Road and Creek Parkway. At Creek Parkway, the plan calls for turn lanes on 322 toward Creek Road and the new road, along with upgraded adaptive signals.
The highway itself would match what Section 101 already built to the west. That means two lanes in each direction split by a curbed grass median, turn lanes at selected spots, eight-foot outside shoulders, and upgraded signals, drainage and guide rail. Anyone who uses the finished stretch between U.S. 1 and Clayton Park Drive already knows the layout.
Because Section 102 is still in design, Garnet Valley residents have a while before any of these intersection changes reach their own commute. PennDOT's project FAQ says business and residential access will stay open during construction. It also says owners whose property is needed for the project should already have been contacted and will be fairly compensated. This is general information, not legal or financial advice. Property owners with questions about their own parcel should go directly to PennDOT or their own attorney.
For now, the only permanent change on the Garnet Valley stretch is the Garnet Mine Road closure, and the active work zones start east of Chelsea Parkway. For a December stop that avoids 322 entirely, Bethel Township is hosting Lunch with Santa on Saturday, December 5, from 11 a.m. to 2 p.m. at 1092 Bethel Road.
If you live along Foulk Road, Colonial Drive or the Bethel Avenue end of town and want to know how a road project this long fits with your own plans, I'm happy to talk through the timeline with you. Robin M Anderson is glad to help. Let's Connect.
Stay up to date on the latest real estate trends.
I provide a hands-on, high-touch approach, guiding every step of your real estate journey with care and expertise. From preparation and marketing to negotiation and closing, I focus on maximizing value and creating seamless experiences. My goal is to deliver exceptional outcomes while building long-term, trusted relationships.